top of page

Estimation Techniques for Road Projects: Earthworks to Asphalt

  • Writer: Gaurav Bhadani
    Gaurav Bhadani
  • Aug 24
  • 3 min read

In road construction, precise estimation of quantities underpins project budgets and contractor cash flow. Underestimating earthworks or pavement layers can lead to severe cost overruns and disputes with clients.


Who this helps

This post is for quantity surveyors, cost engineers, billing engineers and project managers responsible for planning and cost control on highway and road projects in India and the GCC.


Foundations: Elements of a road project

A typical road project consists of site clearance, earthworks (cut and fill), sub-grade preparation, granular sub-base, base course (WMM or crushed aggregate), bituminous base and surface layers, drainage structures, culverts, kerbs and safety installations. Each of these elements must be measured separately with appropriate units—cubic metres for earthwork, square metres for pavement layers, linear metres for drainage pipes and number count for culverts.


Step-by-step estimation process

1. Examine alignment drawings, typical cross-sections and standard drawings to understand the roadway width, pavement composition and structures.

2. Break down the project into chainages (stations) and classify terrain (plain, rolling, hilly).

3. Calculate earthwork volumes using the cross-sectional area method: compute the area of cut and fill at each station, then multiply by the distance between stations to obtain the volume.

4. For pavement layers, compute the area by multiplying the road width (including shoulders) by the length and then multiply by the thickness to get volume; adjust for compaction and bulking.

5. Measure drainage lines, culverts, and structures separately, applying allowances for excavation, concrete and reinforcement.

6. Consolidate all quantities in a bill of quantities and cross-check with design assumptions.


Example BOQ lines for a road

Item | Unit | Quantity | Rate | Amount

Earthwork in cut | m³ | 12,000 | ₹200 | ₹2,400,000

Granular sub-base 150 mm thick | m² | 20,000 | ₹350 | ₹7,000,000

Bituminous surface course 40 mm | m² | 18,000 | ₹450 | ₹8,100,000

Roadside drainage pipe (600 mm dia) | m | 1,200 | ₹1,200 | ₹1,440,000


Plain-text formulas

Cross-sectional area = (sum of parallel side heights) ÷ 2 × base width

Volume of earthwork = area × length between sections

Bituminous mix volume = area × thickness

Material quantity (tonnes) = volume × unit weight


India vs GCC site notes

Indian road projects follow MORTH (Ministry of Road Transport & Highways) specifications with bitumen penetration grades like 60/70, while GCC countries may follow AASHTO or ASTM standards with performance grade bitumen (PG 64-16). Temperature extremes in the GCC require modified binders and thicker asphalt layers. Compaction specifications also differ: Indian projects often aim for 98% of maximum dry density, whereas GCC projects may require 100% or specific core density values.


Common mistakes and how to fix them

- Ignoring side slopes when computing earthwork; fix by including slope dimensions in area calculations.

- Using centreline width only for pavement quantities; fix by adding shoulder and extra widening widths.

- Overlooking shrinkage and bulking factors; fix by applying appropriate bulking factors (e.g., 20% for loose soil).

- Misapplying compaction adjustments; fix by applying field density tests to adjust theoretical volumes.

- Forgetting to include structures like guardrails and road signs; fix by referring to the specification schedule of ancillary works.


Mini QA/QC checklist

- [ ] Verify cross-section drawings and ensure correct scale.

- [ ] Conduct field surveys to confirm ground levels before calculation.

- [ ] Check compaction test results for each layer.

- [ ] Ensure material gradations meet specifications.

- [ ] Verify bitumen temperature during laying and compaction.

- [ ] Confirm that layer thickness is achieved using core samples.

- [ ] Test drainage pipes for leaks and proper bedding.

- [ ] Review the BOQ for logical sequence and completeness.


FAQ

**How often should cross-sections be taken?** Typically every 20 m in plain terrain and every 10 m in hilly terrain or where the profile changes rapidly.

**How do I account for borrow pits?** Measure borrow pit excavation separately and apply shrinkage factors as specified.

**What codes govern road measurements?** Use MORTH Section 900 in India or project-specific specifications in GCC countries.


For deeper learning, see our courses Road and Highway Estimation & Costing (https://www.bhadanisrecordedlectures.com/s/store), Construction Project Planning & Management Level 5 (https://www.bhadanisrecordedlectures.com/s/store) and Tendering & Construction Contracts Management Level 3 & 4 (https://www.bhadanisrecordedlectures.com/s/store).


Level up with BHADANIS – Quantity Surveying & Estimation Level 1 (https://www.bhadanisrecordedlectures.com/s/store)

 
 
 

Recent Posts

See All

Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
bottom of page